Construction schedule risk analysis – a hybrid machine learning approach
File version
Version of Record (VoR)
Author(s)
Lu, Ruodan
Hong, Ying
Brilakis, Ioannis
Griffith University Author(s)
Primary Supervisor
Other Supervisors
Editor(s)
Date
Size
File type(s)
Location
Abstract
The UK commissions about £100 billion in infrastructure construction works every year. More than 50% of them finish later than planned, causing damage to the interests of stakeholders. The estimation of time-risk on construction projects is currently done subjectively, largely by experience despite there are many existing techniques available to analyse risk on the construction schedules. Unlike conventional methods that tend to depend on the accurate estimation of risk boundaries for each task, this research aims to proposes a hybrid method to assist planners in undertaking risk analysis using baseline schedules with improved accuracy. The proposed method is endowed with machine intelligence and is trained using a database of 293,263 tasks from a diverse sample of 302 completed infrastructure construction projects in the UK. It combines a Gaussian Mixture Modelling-based Empirical Bayesian Network and a Support Vector Machine followed by performing a Monte Carlo risk simulation. The former is used to investigate the uncertainty, correlated risk factors, and predict task duration deviations while the latter is used to return a time-risk simulated prediction. This study randomly selected 10 projects as case studies followed by comparing their results of the proposed hybrid method with Monte Carlo Simulation. Results indicated 54.4% more accurate prediction on project delays.
Journal Title
Journal of Information Technology in Construction
Conference Title
Book Title
Edition
Volume
27
Issue
Thesis Type
Degree Program
School
Publisher link
Patent number
Funder(s)
Grant identifier(s)
Rights Statement
Rights Statement
© 2022 The author(s). This is an open access article distributed under the terms of the Creative Commons Attribution 4.0 International (https://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited
Item Access Status
Note
Access the data
Related item(s)
Subject
Persistent link to this record
Citation
Fitzsimmons, JP; Lu, R; Hong, Y; Brilakis, I, Construction schedule risk analysis – a hybrid machine learning approach, Journal of Information Technology in Construction, 2022, 27, pp. 70-93