A graph-based approach for unpacking construction sequence analysis to evaluate schedules
File version
Author(s)
Xie, Haiyan
Hovhannisyan, Vahan
Brilakis, Ioannis
Griffith University Author(s)
Primary Supervisor
Other Supervisors
Editor(s)
Date
Size
File type(s)
Location
License
Abstract
Construction schedules can mitigate delay risks and are essential to project success. Yet, creating a quality construction schedule is often the outcome of experienced schedulers, and what makes it harder is the fact that historic information including decision reasoning was not documented and disseminated for future use. This study proposes a graph-based method to find the most time-efficient construction sequence from historic projects to improve scheduling productivity and accuracy. The proposed method captured the textual, numerical, and graphical features of construction schedules, and was validated on 353 construction schedules obtained from a Tier-1 contractor in the UK. The results indicate that earthwork sequences can be finished in 4.0% of the project time on average, but earthwork sequences are the least time-efficient ones in a construction project (29% delayed), particularly in road construction (88% delayed). This study compared the time efficiency of sequences learned from previous projects with case study sequences. Results indicated that frequent sequences learned from past projects are 26.7% closer to the actual schedule than the planned ones. Results of this study could assist inexperienced schedulers to create more quality construction schedules and project managers to benchmark project performances.
Journal Title
Advanced Engineering Informatics
Conference Title
Book Title
Edition
Volume
52
Issue
Thesis Type
Degree Program
School
Publisher link
Patent number
Funder(s)
Grant identifier(s)
Rights Statement
Rights Statement
Item Access Status
Note
Access the data
Related item(s)
Subject
Information and computing sciences
Engineering
Persistent link to this record
Citation
Hong, Y; Xie, H; Hovhannisyan, V; Brilakis, I, A graph-based approach for unpacking construction sequence analysis to evaluate schedules, Advanced Engineering Informatics, 2022, 52, pp. 101625